Porthos counts costs of construction delays
Netherlands’ flagship CCS project targets 2026 start up after legal challenge derails original construction timetable
The developers of the Netherlands’ flagship Porthos CCS facility are conducting a review of the project’s costs following a two-year delay in construction because of a legal challenge on environmental grounds. The cost of the project, which is a joint venture between Dutch gas company Energie Beheer Nederland, Dutch gas transmission system operator Gasunie and the Port of Rotterdam Authority, has previously been projected at €500m ($544m). But construction has been delayed due to a challenge launched by environmental group Mobilisation for the Environment in November 2021. The Dutch Council of State recently ruled against the environmental group’s claims that nitrogen emitted during the cons
![](/images/white-fade.png)
Also in this section
21 July 2024
Awards experience 20% increase in nominations this year, with submissions from 27 countries
18 July 2024
Platform developed at Scottish university uses advanced simulations and machine learning to find most cost-effective and sustainable combinations of materials for use in carbon capture
18 July 2024
Stockholm Exergi agrees to one of world’s largest deployments of CO₂ liquefication technology to enable transport of emissions captured from biomass power plant
11 July 2024
Watkins will leverage her financial acumen and strategic insight to lead Gulf’s commercial initiatives across media, events, and market intelligence