28 October 2010
Medgaz: Long history, long delay
Medgaz has been driven more by the visions of the two governments than by an immediate commercial need
FOR A project costing €0.9bn ($1.2bn) and with such a long history, there seems to have been little hurry in sending the first gas through Medgaz. When the final investment decision was taken, at the end of 2006, start-up was targeted for the first half of 2009. The target slipped to the end of that year, then to September this year, and now to year-end. Delays were attributed to unspecified technical problems, although laying work was completed on-schedule at the end of 2008. Saipem carried out the technically demanding construction of the 24-inch offshore pipeline, running 210 km from Béni Saf, Algeria, to Almería. The firm's Castoro Sei laid the shallow-water parts of the line, working o
Also in this section
5 March 2026
Gas is a central pillar of Colombia’s energy system, but declining production poses a significant challenge, and LNG will be increasingly needed as a stopgap. A recent major offshore gas discovery offers hope, but policy improvements are also required, Camilo Morales, secretary general of Naturgas, the Colombian gas association, tells Petroleum Economist
4 March 2026
The continent’s inventories were already depleted before conflict erupted in the Middle East, causing prices to spike ahead of the crucial summer refilling season
4 March 2026
The US president has repeatedly promised to lower gasoline prices, but this ambition conflicts with his parallel aim to increase drilling and could be upended by his war against Iran
4 March 2026
With the Strait of Hormuz effectively closed following US-Israel strikes and Iran’s retaliatory escalation, Fujairah has become the region’s critical pressure release valve—and is now under serious threat






