28 October 2010
Medgaz: Long history, long delay
Medgaz has been driven more by the visions of the two governments than by an immediate commercial need
FOR A project costing €0.9bn ($1.2bn) and with such a long history, there seems to have been little hurry in sending the first gas through Medgaz. When the final investment decision was taken, at the end of 2006, start-up was targeted for the first half of 2009. The target slipped to the end of that year, then to September this year, and now to year-end. Delays were attributed to unspecified technical problems, although laying work was completed on-schedule at the end of 2008. Saipem carried out the technically demanding construction of the 24-inch offshore pipeline, running 210 km from Béni Saf, Algeria, to Almería. The firm's Castoro Sei laid the shallow-water parts of the line, working o
Also in this section
16 April 2026
Demand for oil is falling because supply cannot meet it, not because it is no longer required
16 April 2026
The continent has an immediate opportunity to make the most of its energy resources by capturing gas that is currently slipping away
15 April 2026
The continent is seeing political pushback to climate plans, corporate reassessment of transition goals and rising supply risk in a fractured global order
15 April 2026
The Middle East energy crisis may turn out to be pivotal to the industry’s long-term expansion, but significant challenges still stand in its way






