Uganda’s oil production delayed until 2018
Seven years after oil was discovered in inland Uganda, first flows are still in the distant future
When oil was discovered on the shores of Uganda’s part of Lake Albert in 2006, there were forecasts that production would start within five years or so. The reality, after years of disputes, is that first oil, together with the start-up of the inland refinery the government is insisting on, will not be achieved for another five years at the earliest. In October, the government firmed-up its plan for a refinery with a call for a partner to operate and take a 60% interest in the facility, initially of 30,000 barrels a day (b/d) capacity but later to double, which is to be constructed near the oilfields, about 1,300 km from the coast (see box). The authorities’ schedule envisages selecting the
Also in this section
16 April 2026
Demand for oil is falling because supply cannot meet it, not because it is no longer required
16 April 2026
The continent has an immediate opportunity to make the most of its energy resources by capturing gas that is currently slipping away
15 April 2026
The continent is seeing political pushback to climate plans, corporate reassessment of transition goals and rising supply risk in a fractured global order
15 April 2026
The Middle East energy crisis may turn out to be pivotal to the industry’s long-term expansion, but significant challenges still stand in its way